Perspectives
Perspective 017Programme Scoping

Programmes do not fail because they were too ambitious. They fail because their assumptions were never tested.

A practitioner's note on what scoping really is: the discipline of refusing to write a number down until you can show your working, and the register that holds the plan together when the numbers start to move.

By Everett MorganEarly Autumn 20268 min read
Stacked customer files on a quiet office desk under low evening light
Executive summary

Programmes rarely fail because they were too ambitious. They fail because the numbers underneath the ambition were never tested before the Steering Committee approved them.

This is a companion note to Guide 009, Scoping an AML Remediation Programme. The guide sets out the full scoping cycle, decision by decision. This piece sits on the single most useful artefact I produce in a scoping, and the discipline that makes the artefact worth having.

Key takeaways
  1. 01

    Programmes I am asked to recover are rarely too ambitious. They are programmes whose ambition was priced against assumptions nobody had tested. The volume came from a single query. The productivity came from a benchmark. The capacity was divided out of the productivity without a working week underneath it.

  2. 02

    Scoping is mostly the discipline of refusing to write a number down until you can show your working. The team will resist this in week one. The Steering Committee will resist it more. The two weeks spent insisting on a real population query, a real pilot and a real capacity model are the two weeks that decide whether the programme delivers.

  3. 03

    The single most useful artefact I produce in any scoping is the assumptions register. Every number the plan depends on, with the basis on which it was derived, the named owner who derived it, and the trigger at which it must be re-tested.

  4. 04

    The register is rebuilt three times before mobilisation. By the time the Committee approves the plan, the register has more entries than the budget has lines. That is the right shape.

  5. 05

    Programmes recover when the register is opened in month four and the changes are governed. They fail when the register does not exist, and the changes are absorbed in silence until the gap between the plan and the work is wider than the programme can close.

  6. 06

    If your scoping paper does not have an assumptions register attached, the paper is not finished. It is a draft for a paper that has not yet done the work it needs to do.

I have been asked, more than once, to recover programmes that were described, when I arrived, as too ambitious. That has almost never been the problem. The ambition was rarely the issue. The issue, in every case, was that the ambition had been priced against numbers nobody had stress-tested.

The volume number had come from a single query against a production database, run by one person, against a cut-off that was never reconciled. The productivity number had been lifted from a benchmark slide that nobody could trace to a particular firm or a particular type of file. The capacity number had been divided out of the productivity number without a working week underneath it: no allowance for QA, no ramp-up, no attrition, no leave. The plan looked precise. None of the numbers were robust.

What scoping actually is

Scoping is mostly the discipline of refusing to write a number down until you can show your working. The team will resist this in the first week. The Steering Committee will resist it more. There is always a date by which the plan has to be tabled, and the temptation to fill the gaps with a benchmark or an estimate is enormous.

The two weeks spent insisting on a real population query, a real fifty-file pilot and a real capacity model built in layers are the two weeks that decide whether the programme delivers. They are also the weeks the Programme Sponsor is most likely to argue against. The argument is usually some version of: we need to start the work. The honest answer is that the work cannot start until the numbers it is sized against are numbers somebody is willing to defend.

The artefact that holds the plan together

The single most useful artefact I produce in any scoping is the assumptions register. Not the plan, not the budget, not the slides. The register. Every number the programme depends on, with the basis on which it was derived, the named owner who derived it, and the trigger at which it must be re-tested.

By the time the Committee approves the plan, the assumptions register has more entries than the budget has lines. That is the right shape.

The register is rebuilt three times before mobilisation. Once at the end of the population work. Once at the end of the pilot. Once at the end of the mobilisation phase, the week before the Committee approves the plan. Each rebuild changes numbers. Some change materially. The discipline is that the changes are visible: the Committee sees them, signs them off, and the plan that goes forward is the plan that has been rebuilt around the latest version of the assumptions, not the plan that was tabled in week three.

Why the register matters in month four

The numbers will move. They always move. The question is whether they move inside a register the Committee can see, or outside a register that does not exist. Programmes recover when the register is opened in month four and the changes are governed. They fail when the changes are absorbed in silence until the gap between the plan and the work is wider than the programme can close.

The two versions of the programme had the same ambition at the start. Only one of them did the scoping work to make the ambition deliverable. The other ran on assumptions that were never tested, and on a Steering Committee that never saw the assumptions move because the register did not exist to hold them.

What I would do this week, if I were the Programme Sponsor

Open the latest scoping paper. Look for the assumptions register. If it is not there, ask the Programme Director for it, in writing, before the next Committee. If the register is there, look at the column for the named owner of each assumption. If the owners are missing, the register is a document, not a working artefact. If the owners are named, look at the trigger column. If the triggers are missing, the register will not be re-tested when the work begins. If the triggers are there, the register is doing its job.

Guide 009 sets out the full scoping cycle, including the population query, the file standard, the productivity pilot, the capacity model in layers and the contingency conversation the Committee should be having at mobilisation rather than at month six. Download the full guide and use the assumptions register at Appendix A as the starting point for your own.

About the author
Everett Morgan
Founder & Principal Adviser, Claritas Risk Advisory

Everett has more than twenty years' experience in financial crime, AML governance, regulatory compliance and operational risk gained within Deutsche Bank, Morgan Stanley and BNP Paribas. He established Claritas Risk Advisory to provide smaller regulated financial institutions with experienced independent judgement, practical insight and proportionate recommendations.

Need an independent perspective?

Preparing for regulatory change starts with understanding where your organisation stands today.

If you would like to discuss your financial crime framework or explore how Claritas Risk Advisory can help, I would be pleased to arrange a confidential conversation.

Let's start with a conversation